RAILS ON RUBBLE - COMPONENTS
ABOUT THE SYSTEM
There are three different cross-ties used on rubble:
- wooden cross-ties
- reinforced concrete cross-ties
- prestressed concrete cross ties of
Rails are fixed to the wooden cross-ties with bolted bonds or spring clamps.
Stages of the crane runway installation:
- Excavation of the crane runway channel, filling it with rubble
- Laying of the crane runway pavement
- Runway lining and covering
RAIL PADS
Rail pads distribute the wheel load over a larger area under the rail. In this way the load concentrations are reduced event of 50%. That reduces local stresses which cause many problems in crane runway exploitation (bad alignment, wheels falling from the rail, excessive wear of the rail head etc.).
DISCONTINOUS RAIL SUPPORT MK II | CONTINOUS RAIL SUPPORT MK VII |
CRANE RAILS
Not everyone knows that rail has its beginning and end, right and left side and many other characteristic features. Our duty is to choose the right rail (taking into consideration both technical and economical issues) and deliver it to the Customer in expected period of time.